31 January 2020, 5:09 AM
Motorists are advised of changed traffic conditions and night work on the Pacific Highway from Monday 3 to Sunday 9 February for the Woolgoolga to Ballina upgrade, weather permitting.
From Monday, there will be six days of work on the Pacific Highway between Mororo and Woodburn to install drainage, carry out earthwork and paving, and remove traffic barriers to allow vehicle access to site. Motorists can expect traffic control and a reduced speed limit of 60km/h and short stoppages at times between 6am and 6pm.
Also from Monday, there will be five days of work next to the Pacific Highway at Chatsworth Island to carry out work on the Chatsworth Island North overpass bridge. Motorists can expect traffic control and short stoppages at times between 6am and 6pm.
Further south from Monday, there will be five days of work next to the Pacific Highway at Maclean for excavation work. Southbound motorists can expect a reduced speed limit of 60km/h between 6am and 6pm
From Tuesday, there will be four nights of work on the Pacific Highway at Woodburn to install traffic safety barriers, remove line marking and carry out pavement testing. Motorists can expect lane closures and traffic control between 6pm and 6am.
Also from Tuesday, there will be four days of work on the Pacific Highway at Glenugie to install electrical cables, lighting poles and signage. Motorists can expect lane closures, traffic control and short stoppages at times between 7am and 6pm.
On Friday, there will be one night of work on the intersection of the Pacific Highway and Ryans Lane at Chatsworth Island to carry out asphalt work and line marking. Motorists can expect lanes closures and traffic control between 6pm and 6am.
Additional changes to local roads
From Monday, there will be five nights of work on the heavy vehicle underpass at the Yamba interchange and Oval Link Road at Harwood to carry out asphalt work. Motorists can expect lane closures and traffic control between 6pm and 6am.
Traffic control will be in use on Woodburn-Evans Head Road, Woodburn for up to five days from Monday to allow vehicles to access the project site and carry out drainage work. Motorists can expect lane closures and traffic control between 6am and 6pm.
Also from Monday, there will be five days of work on Tuckombil Road at Woodburn to carry out road maintenance, asphalt work and vegetation removal. Motorists can expect lane closures and traffic control between 6am and 6pm.
From Tuesday, there will be three days of work on the Old Pacific Highway at Glenugie to install electrical cables, lighting poles and signage. Motorists can expect lane closures, traffic control and short stoppages at times between 7am and 6pm.
On Friday, there will be one night of work on Wondawee Way and Trustums Hill Road at Woodburn to remove traffic barriers and carry out asphalt work. Motorists can expect lane closures and traffic control between 6pm and 6am.
The old Mororo Bridge is temporarily closed while drainage is installed.
Motorists are advised to drive to the conditions and follow the direction of signs and traffic control. Transport for NSW thanks motorists for their patience during this time.
For the latest traffic updates download the Live Traffic NSW App, visit livetraffic.com or call 132 701.